Hyderabad’s KBR Park traffic project has changed dramatically while work was already underway. The original plan called for seven steel flyovers and seven underpasses at different junctions around the park, with the project cost eventually revised from ₹826 crore to ₹1,090 crore. Construction had begun at several locations, including pillar foundations and excavation for proposed underpasses. Now, that network has been dropped.
The government has approved a 4.3-km, six-lane elevated corridor connecting Jubilee Hills Check Post through Mugdha Junction towards Muffakham Jah College, with a ramp towards Banjara Hills Road No. 1. The two revised packages together remain worth ₹1,090 crore. The government has also cancelled the earlier NFCL Junction flyover and TV9 Junction works and revoked the Letter of Award issued to KNR Constructions. MEIL, the existing EPC contractor, will execute the revised packages.
So what changed?
The original KBR project had already moved into execution. By the middle of this year, GHMC was reporting excavation and pillar work at multiple locations around KBR Park, Jubilee Hills and Banjara Hills. The project was intended to address congestion through a combination of flyovers and underpasses rather than one continuous structure.
But the project ran into problems. Tree-felling and translocation around KBR Park became the subject of legal proceedings, with a stay affecting work within the park’s eco-sensitive zone. At the same time, land acquisition emerged as a major issue because the original design required properties to be acquired along some of Hyderabad’s most expensive stretches.
Then the traffic arrangement around the park changed.
In August, Hyderabad Traffic Police introduced a clockwise one-way system around KBR Park. It was partly necessitated by the construction itself, which had reduced available road space, but the arrangement subsequently appeared to improve traffic movement.
By October, GHMC Commissioner R.V. Karnan was saying that the response to the one-way system was one of the reasons the earlier infrastructure proposals were reassessed. The environmental and legal problems with the original configuration were another factor.
This is what makes the sequence unusual. The government did not arrive at the new design before construction began. It arrived at it after the original project was already being executed and after the one-way system provided a different way of managing traffic around the park. The one-way arrangement is now expected to continue as part of the longer-term traffic plan.
The engineering approach has changed. The original project treated the problem as a series of individual junction bottlenecks: build a flyover or underpass at each location and create signal-free movement around the park.
The revised proposal instead puts through-traffic on a continuous elevated route. The 4.3-km corridor is designed to provide signal-free movement across five major junctions, while surface traffic continues to use the surrounding roads.
The government also says the revised alignment reduces extensive ground-level work and property acquisition, while keeping the elevated structure outside the park’s eco-sensitive zone. That is the core defence for the redesign: the traffic problem remains, but the earlier solution is no longer considered the most efficient way of addressing it.
This is where the latest controversy gets more complicated. The government says the revised design could save around ₹1,200 crore compared with the earlier multi-component proposal, approximately ₹800 crore in land acquisition and ₹400 crore in construction costs. (newindianexpress.com)
But the revised project itself still carries the same ₹1,090-crore sanctioned cost.
That has become one of the BRS’s main questions in the last few days. There are now questions on how a project in which seven flyovers and seven underpasses are being cancelled can retain essentially the same overall price tag for a single elevated corridor. The report alleges that the earlier cost estimates are effectively being adjusted into the new project and raises questions about who benefits from the redesign. Those are allegations, not established findings.
There is a more concrete issue underneath that political argument: the revised government order has changed the scope and contractor arrangements without changing the overall sanctioned amount. Package I remains ₹580 crore and Package II ₹510 crore, although the government’s revised internal benchmarks for the two packages are lower, ₹365.85 crore and ₹349.31 crore respectively.
That makes the actual cost accounting worth examining rather than simply comparing the headline ₹1,090-crore figures.
BRS’s criticism has become broader over the past few days.
BRS MLA P. Vivekanand has claimed that work worth ₹100–200 crore had already been completed and that around 1,000 trees had been removed before the original project was halted. He has questioned why the government began a project of this scale before changing its approach and demanded accountability for the expenditure. The ₹100–200 crore figure is a claim, the government has not publicly provided a comprehensive figure for expenditure that becomes redundant because of the redesign.
The latest BRS criticism goes one step further: if the original works are being cancelled and the revised design is supposed to save money, why does the replacement still carry a ₹1,090-crore project value, and how exactly are the old and new costs being reconciled?
That is a more specific question than simply accusing the government of a U-turn.
The government says it is not abandoning the idea of improving traffic around KBR Park. It is abandoning the original way of doing it.
Seven flyovers and seven underpasses have given way to one continuous elevated corridor. The one-way system is being retained. Some junction-level works are being cancelled. The contractor arrangements have been changed. The government says the new configuration reduces land acquisition, avoids the eco-sensitive zone and saves money compared with the earlier design.
But because construction had already started, the transition creates a second issue beyond traffic engineering: what happens to the money, contracts and physical works associated with the original design?
That is where the KBR story now sits.
The question is no longer simply whether Hyderabad needs another flyover. It is whether the new corridor is genuinely a better solution, and whether the government can clearly account for the journey from ₹826 crore, to ₹1,090 crore, to seven flyovers and seven underpasses, and finally to one 4.3-km elevated corridor.
This post was last modified on 7 October 2026 3:58 pm
Tamil Nadu chief Minister Thalapathy Vijay is a pretty popular face in Andhra Pradesh and…
https://youtu.be/4wlX92MXVLo?si=Tx3Pp4npK1yuF0Tf Friendship is one of the most beautiful emotions of childhood, and Summer Holidays is…
Ram Charan and Sukumar’s much-awaited reunion, RC17, is finally moving ahead. The film’s pooja ceremony…
https://youtu.be/txL-cz17oqM?si=5QyfIkpe8HJDIkDc Ranabaali is one of the most interesting films in the making, especially because director…
TDP is now planning to fill nominated posts without depending on recommendations or referrals. Party…
The success of a film is ultimately measured by the response it receives from its…